The FGC project contracted by Huaxing for Longkou Waste Incineration Power Plant in Yantai, Shandong passed 168 hours trial operation
2022.11.02
The flue gas cleaning (FGC) project contracted by Huaxing for Longkou WTE plant in Yantai, Shandong passed 168 hours of trial operation on Oct. 6, 2022.
The plant will build a 600 t/d waste incineration line for municipal solid waste treatment at one time. The FGC adopts the treatment process of "SNCR denitration + semi-dry deacidification + dry deacidification + activated carbon injection + bag filter + fly ash conveying, storage, and stabilization (reserved SCR denitration system interface and position)". It is an EP project of Huaxing.
At present, Huaxing's achievements in Shandong include Zhucheng, Weifang Phase I & II, Weifang Gaomi, Mouping, Tai'an, Gaomi, Zichuan, Linyi Phase II, Xiaojianxi, Huangdao, Linzi Phase I & II, Linyi Lanshan, Yishui Phase II, Wendeng, Laixi, Dezhou, Longkou, Yiyuan, Changle, Shanghe, Yanzhou, Zaozhuang, Zhangqiu Phase II, Laizhou, Yishui Phase I, etc.
For more information, please click or scan below!

Follow us!